Visual

Mathews Residence

Job #24019 · 9715 NE 198th St, Bothell · Renovation + Addition
Dashboard 101 · How this works
Construction — Week 1

What you need to know right now

Construction officially kicks off today — demo and site prep are underway, and the build phase has begun. Permits are in their final reviews and material selections are moving.

This overview updates from the current construction phases. The notes here are pulled from the summary line of each active phase.

Project Overview
Job #24019
Clients
Chris + Megan Mathews
Address
9715 NE 198th St, Bothell
Type
Renovation + Addition
Scope
Full renovation and addition to the bedroom wing — new bedrooms, bathrooms, and reconfigured layout — plus targeted updates throughout the rest of the house.
Build start
July 13, 2026
Completion
Feb 15, 2027 (target)

Build Schedule

Jul 13 '26Build Start
Feb 15 '27Completion
Jul '26
Aug
Sep
Oct
Nov
Dec
Jan '27
Feb
Preconstruction & Demo Started today – Aug 4 · In Progress
Excavation & Foundation Aug 3 – Sep 21
Framing & Dry-In Aug 31 – Oct 21
Rough-In Oct 6 – Nov 6
Drywall & Paint Nov 9 – Jan 5
Interior Finishes Nov 26 – Feb 4
Cabinets & Trim Nov 24 – Jan 7
Fixtures & Appliances Dec 3 – Dec 10
Exterior Elements Weather dependent · TBD
Final Close-Out Dec 10 – Feb 15
Active now Upcoming Today
Week by Week

Schedule

Week of July 13 Current Week

  • Build phase kicks off — TODAY, Jul 13 Team
  • Demo & Site Prep begins — TODAY, Jul 13 Crew
  • Subcontractor walk-throughs on site Jon + Subs
  • Carl's first pre-construction walk-through Carl
  • Scope Snapshot & final bid wrap — Jul 13 Frank / Carl
  • Final contract prep begins — Jul 16 Frank / Jon
  • Jobsite setup begins — Jul 16 Jon

Week of July 20

  • Permit second review window closes — Jul 23 City
  • Selective demo begins — Jul 22 Crew
  • Electrical / plumbing disconnects — Jul 22 Crew
  • Temporary protection installed — Jul 22 Crew
Project Journal

Who's Got the Ball

4Not Started
1In Progress
1Complete ▾

Every question, request, and RFI lands here first — this replaces email. Click a team to see their items; click again to collapse. Use the Design Journal form to add an entry.

6
All
0
Homeowner
2
Purchasing
0
Vendor
1
Design
1
Build
1
Client Rep
0
Structural
0
Civil
0
Subcontractor
Materials & Selections

The Order Board

0Not Started
22In Progress
0Complete

Where the ball sits in finalizing all material orders — who's in charge of making sure each order gets done. Click a number to see that list; click again to collapse.

22
All
2
Homeowner
17
Purchasing
2
Vendor
1
Design